About Nalanda facilities – expansion, development, addition, etc.
Today marks the 160th day since the Nalanda Centre Building Expansion Project began in mid-May. Overall, the annex building is 83% completed, while the remaining work is progressing well. The new roof structure spanning two lots is also 100% done. For these past few months, we are very thankful to have achieved a 100% safety record, thanks to good cooperation from the consultants, builders, sub-contractors, and Nalandians.
Read moreToday marks the 150th day since the Nalanda Centre Building Expansion Project began. The new roof structure was installed last week, and work is progressing well on all levels. The Building Committee is working hard to ensure the earlier hand-over of Levels 2 and 3 so as to facilitate the hosting of major upcoming events such as “Sangha Day”, holiday camps, and members’ convention.
Read moreToday marks the 140th day since the Nalanda Centre Building Expansion Project began. Work is progressing smoothly on all levels, especially at Level 4 and the roof structure. The Building Committee has indicated that Levels 2 & 3 may be completed earlier and handed over to Nalanda by mid-October. This timely development will come in handy as Nalanda Centre will be hosting major events in the last quarter of the year, such as “Sangha Day”, holiday camps, members’ convention, and group visits. Read more
Today marks the 130th day since the Nalanda Centre Building Expansion Project began. In just another 50 days, the construction and renovation work should be wholly completed! Currently, work is concentrated at Level 4 and the roof structure. We have also started landscaping the surroundings of Nalanda Centre. Volunteers spent a few days last week to clean up the neighbourhood, and planted suitable shrubs to enhance the experience of visitors to the Centre.
Read moreToday, we reached the 120th day milestone since the Nalanda Centre Building Expansion Project began. In another 60 days, the construction and renovation work would be wholly completed. We are happy and thankful that the project is on schedule and progressing well, and furthermore with a perfect safety record! The building construction is now concentrated at Level 4. With the floor slab completed, the workers are busy working on the roof structure presently.
Read moreThe Nalanda Building Expansion Project is progressing steadily 111 days after work started. The building construction has reached Level 4 and is on schedule to be completed in another 70 days. We look forward to its successful completion because bigger and better facilities mean many more people will be able to benefit from holistic Buddhist education.
Read moreToday marks the 105th day work began on the Nalanda Centre Expansion Project. We are glad and thankful to share that to date, 52% of the overall work has been successfully completed. Work is progressing rapidly on the upper floors of the building, with the Level 4 Dhamma Hall gradually taking shape.
Read moreToday marks the 100th day work began on the Nalanda Centre Expansion Project! Work is progressing rapidly on the upper floors of the building, with plumbing and M&E components catching up. With the current rate of construction, we are optimistic that the project can be completed on schedule in another 80 days.
Read moreToday marks the 90th day that work began on the Nalanda Centre Expansion Project, and also the pivotal mid-way point towards its completion! Construction has been progressing steadily with 100% safety record. Work is now concentrated on the two upper floors of the 4-storey building.
Read moreToday marks the 80th day work started on the Nalanda Centre Expansion Project. As we draw closer to the scheduled half-way point of reconstruction, the building itself is gradually taking a more concrete and complete shape!